09-Apr-08 Upper level brickwork
16-Oct-08 Upper roof complete
19-Nov-07 Basement complete
18-Dec-07 Ground_slab
22-Feb-08 Brickwork ground level & upper slab formwork

Floor area: 950 sqm
Finishes: High spec / high detail finishes including slate roof, copper roof plumbing, stone external cladding, Oak doors and joinery, Sheaok parquetry flooring, Venetian plaster, marble tiling
Work scope : Turnkey contract from demolition of existing building, construction of new residence to carpeting and coordination of landscaping
Duration: Sep-07 to Mar-10 completed on time
25-Sep-07 Demolition
11-Oct-07 Excavation and lift-well