21 Dec 06
Upper level plaster
21 Feb 07
Upper level lockup
21 May 07
Tiling completed
30 Jul 07
Practical completion
Sep 05 -May 06 Documentation
08 Sept 06
1st Plate
31 Oct 06
2nd Plate
20 Nov 06
Roofing
RESIDENTIAL BUILDERS


6 James Rd Swanbourne

 
Project: New double storey family home

Floor area: Indoor 470 sqm, balcony /cabana / alfresco 160; total 630 sqm

Contract Schedule: 18 mths.

Completion Schedule: 14 mths to handover

Work scope : Conceptual design, detailed design, construction, hard landscaping design & construct.

01 June 06
Building License
07 July 06
Ground Slab
Completed house
Construction records